Quick answer
Four areas are examined: whether wash programs match shared-product risk; whether acid, alkali and sanitizer concentration, temperature and time are quantified and recorded; whether dead legs and shared branches exist; and whether the final rinse is verified. A beverage plant in Guangzhou files CIP parameter curves with each batch and re-verifies after detergent changes. Document review first checks the CIP flow diagram to identify blind pipes and return-flow risks early.
Detailed explanation
Four CIP review points
Auditors compare the diagram with actual piping, check programs against shared-product risk, verify that acid, alkali and sanitizer concentration, temperature, time and flow are quantified, and confirm a final-rinse conclusion. Items logged only as per procedure without values draw questions.
Return-flow and dead-leg risks
For shared stations, auditors check return-tank mixing, discharge of return liquid, and branch-valve backflow. Dead legs, sample valves and bypasses must be pointed out on site; sealed old branches need photos and numbers.
Parameter curves and records
Each CIP run should keep conductivity, temperature and time curves or printouts linked to the lot number. Manually entered parameters need operator and verifier signatures. After changing detergent brand or concentration, a fresh verification should be performed.
Manual washing beyond CIP
Tank tops, dosing ports, seals and filler heads outside CIP coverage need separate manual dismantling steps and visual checks in the SOP. Auditors often ask for one dosing port to be dismantled on site to test whether manual washing genuinely happens.
Applying this answer to your plant: three checks
A FAQ answer is general. Before acting on it, check your own situation to find documentation gaps early.
Match raw materials and lines
Map the raw materials, additives and process steps mentioned in the answer to your formula, suppliers and lines. Shared lines need changeover and cleaning validation; dedicated lines need segregation records.
Check documents against batches
Confirm that origin certificates, slaughter or purchasing records, test reports and intake ledgers can be traced by batch. Names, specifications and process descriptions must match the application.
Align with the shipping gateway
For your actual route through Tianjin, Dalian, Manzhouli or Khorgos, check certificate product scope, invoice description, packing batches and cold-chain temperature records to avoid inconsistent documents.
These are general checks, not a certification conclusion. Document requirements and certification decisions follow Indonesia’s BPJPH rules and the formal assessment.
Still have questions?
Tell our consultants your product category and target market, and we will help you map out the path and the documents required.